the total price of the house in installments as per following schedule either in cash or by a Demand Draft / Pay Order, drawn on a scheduled Bank at Lahore in favour of
| 1st Installment |
15 % As advance amount at the time of signing the Agreement. |
| 2nd Installment |
15 % of contract amount after completion of foundation works upto plinth level. |
| 3rd Installment |
10 % of contract amount after completion of brick masonry works upto G.F. slab level. |
| 4th Installment |
10 % of contract amount after completion of casting of R.C.C roof slab of Ground floor. |
| 5th Installment |
10 % of contract amount after completion of brick masonry works in First Floor. |
| 6th Installment |
10 % of contact amount after completion of casting of R.C.C slab of First Floor. |
| 7th Installment |
10 % of contract amount after completion of all internal plastering works with underground piping. |
| 8th Installment |
5 % of contract amount after completion of all internal flooring and bathroom tile works. |
| 9th Installment |
5 % of contract amount on finalization, including fixing of electric and sanitary fittings. |
| 10th Installment |
4 % of contract amount prior to taking possession by the Client. |
| 11th Installment |
1 % of Contract amount after Three month of possession. |
The above payment schedule is for a double storeyed construction and shall be adjusted if the house is a single storey job.